Code
CG.13.11
Season
2013
Narrative

Weather: It was a sunny day with an agreeable breeze in the morning. Since 10h 00 am, the wind was pretty strong.

Workers:
1- Gregor
2- Roman
3- Rolland
4- Zarzan
5- Karlos
6- David
7- Harmand (once in the afternoon, he left to help his friend to take care of their sheeps).

I would like to finish T35 a soon as possible (before I have to live Gegharot to Tsagahovit). Unfortunately, because of the wind, we could not work well. So we went to T 31 to finish removed the locus 100 (cleaning the washed soil). We had not still finished at the end of the day (it is hotter in this part of the mountain and the guys are not efficacy as when they are in the other side). In the morning, we just had the time to start the locus 05. We found metal in it. I analyse that the locus 05 is a wash soil too. I will make one locus with the 03 and 05 one at the end of the trench. I made a new elevation point because the ancient one was so high that, my workers and I can not afford it. In T34, we had found a stone tool and a ceramic disc
Z: 2297.29 MINUS 166 cm = New Elevation point = 2131.29.