Unfortunately a family matter prevented me from making it out to site today. Armine took my place and ran operations in T38. Judging by what I encountered upon returning the site most of the day was spent articulating wall (locus 15) and beginning the indefinite process of cleaning up the collapse to the west (locus 13). Through this work it became evident that wall (locus) 10 continues northward and curves in a manner parallel to wall (locus) 9. It also seems possible that under the locus 13 rubble there is a wall that runs E/W connecting the two architectural features. We will continue to articulate and clean in order to begin investigations of the cultural levels later this week.