Today we kept excavating locus 4 and almost finished uncovering the third course of stones belonging to wall 1. However, we are still far from detecting a floor/living level associated with a supposed indoors environment. Furthermore, the area along the W facade of Wall 1 is still rather limited to get a wider sense of the situation.
Later in the morning we set up a further extension of T46 towards N (5.00 x 2.50m) in order to track the length of the wall in NW direction. The day ended with initial removal of the topsoil from this extension.