06.30.2006. ATS took more photos of Burial 1 this morning, with the capstone, locus 6. Then we worked on breaking the capstone and rolling the pieces out of the trench. By about 2 it was cleared out and we were just starting to clean off some of the dirt when it rained, so we stopped work in it.I took some points to draw the large rocks in the center of Burial 2.We also layed out the trench for Burial 3 to the east of Burial 2 (7.5x6.5m), took elevations (datum E,F), photos, and then started clearing off locus 1, the topsoil. The trench may need to be expanded, from the top it looks like there are several large stones that are not part of the cromlech construction, but since including these would have significantly increased the size of the trench, I just ran the edges over them.ATS also shot the datum points, and corners of the 3 trenches.